1.Reserved land for installation
2.Basic excavation
3.Basic compaction
4.Basic rubble laying
5.Basic concrete placing
6.Floor steel reinforcement placing
7.Floor double grid-type placing
8.Floor concrete placing
9.Wall, load cell support grid-type placing
10.Wall concrete placing
11.Truck scale substructure ¨ç
12.Truck scale substructure ¨è
13.Truck scale assembly ¨ç
14.Truck scale assembly ¨è
15.Load cell installation
16.Summing box installation
17.Truck scale upper plate assembly
18.External indicator installation
19.Weight adjustment (Calibration)
20.Weight adjustment (Calibration)
21.Indicator installation
22.Weight PC system installation
23.Truck scale installation complete
24.Calibration certificate